Portal entrust KOHLER with their critical power for over 15 years

Project Overview

Location

Nottingham, UK.

Critical Load

Business critical IT infrastructure and communications.

Challenge

An ageing UPS system needed to be replaced for a data center facility to ensure continued support and maintenance to critical assets.

Solution

Installation of new UPS units and a bespoke steel platform to protect DC supply. The transformerless three-phase UPS unites are parallelable up to 5MVA and offer a reduced footprint and energy saving technology.

Background

Kohler Uninterruptible Power (KUP) have recently helped Polar Air Limited, a mechanical and electrical engineering company, replace an aging critical power protection infrastructure for Portal Group UK, who manage a data centre facility for a bluechip company.

The ageing system had been commissioned and maintained by KUP for over 15 years and was identified as coming up to the end of its support by a Field Service Engineer.

“At a routine preventative maintenance visit at the beginning of 2019, the uninterruptible power supplies were identified as coming towards their end of life, which we discussed with Polar Air,” explains John Inman, Business Development Manager at Kohler Uninterruptible Power.

During the discussions, Polar Air and Portal understood the importance of replacing the UPS systems. Andrew Fitch, from Polar Air adds,

“after an informed conversation with John, we realised the UPS was coming to the end of its life, and to ensure continued support and maintenance to the critical asset we needed to look at a new power protection solution.”

Challenge

The previous system included four PowerWAVE 5000 Maxi uninterruptible power supplies, which worked in conjunction with a standby Generator capable of supporting a load of circa 750kW (N+1). They were located in a dedicated UPS room, external to the main data centre halls.

“It was important that we tried to match the new proposed system to what was already in place, Portal only reported a current system load of 200Kw, and it was therefore an ideal time for the works to be undertaken. Normally, when working with our customers, we do not offer more than what is required.” John Inman explains.

Solution

KUP recommended four replacement PowerWAVE 6000 250kVA each uninterruptible power supplies for this infrastructure, with three strings of Yuasa VRLA batteries. The PowerWAVE 6000 is a transformerless three phase UPS, parallelable up to 5MVA. Offering both intelligent energy management and maximum power protection, it uses less energy, achieves significant cost reductions, saves on valuable floor space and has a reduced impact in the environment.

The original installation was configured with the DC cabling running between the UPS modules and the battery strings housed within steel trunking fixed directly to the floor. This presented a challenge to the design team, as it would have prevented the units being swapped out without a complete system shutdown, which simply could not happen given the downstream business critical equipment being supported.

This was overcome by the installation of a permanent but accessible bespoke steel platform to allow each UPS modules to be swapped out independently with the remaining units still supporting the load.

Result and Impact

Replacing any UPS can be a costly exercise, but at KUP we explore how we can use what is already in place, to save not only money but time as well. Commissioned in July 2020, Portal Group UK continues to be a loyal customer to KUP.

“We were thankful that KUP could fully utilise existing components, like the battery racks, DC cabling and DC isolators – it saved Portal further expenditure, and it greatly increased the speed and ease of commissioning.”

Andrew Fitch, Polar Air.

“With excellent service offerings and knowledgeable staff, we know we are working with a trustworthy supplier who have our best interests at heart.”

Derek Clogg, Managing Director at Portal Ltd.

PM: John Inman, KUP Business and Development Manager

Client: Polar Air and Portal Group UK

If you are looking for a sales and service solution for your power protection equipment, please get in touch with our team at [email protected]

You may also be interesed in....

Need an answer quickly? Our team of experts are on hand to help, call 0800 731 3269.

More Case Studies